Federal Ministry of Works (HDMI) Phase II

HDMI Phase II

1.0 Introduction

The Federal Ministry of Works (FMW) under its statutory responsibilities over Federal Road Network, introduced the Highway Development and Management Initiative (HDMI) to attract sustainable investment and funding in the development of road infrastructure and maximization of the use of assets along the Right of Way (ROW). The rationale behind the private sector engagement is to provide alternative source of financing road development and management in the country. The first phase of the initiative entailed the concession of 12 Federal Highway Corridors, Nine (9) of which have attained Commercial Closes. Nigeria has the world’s largest population of people of African origin with about 215 million inhabitants. It is also Africa’s largest economy with a vast land area that is connected by over 36,000km of Federal road network. This has served as a significant tool for economic development over the years. The FMW has been constrained in fulfilling this remit of road development and management due to financing constraints. The FMW in line with global best practices has established a Public Private Partnership (PPP) model where private partners can tap into the numerous commercial opportunities available along the Nigerian highways. The PPP model involves concessioning the Right of Way of highways to technically and financially capable private companies who would manage them and develop the road furniture along the route. The successful implementation of this initiative would spur economic growth in the country. It will bring about meaningful development as well as open up various regions to new markets, thereby creating thousands of jobs and new businesses.
The 2nd Phase of the Initiative is to be procured via a Competitive Dialogue process. The terms and conditions for project implementation with selected concessionaires will be set out in the Concession Agreement to be mutually negotiated.

2.0 Project Objective

The overall objective of the selection process would be the successful procurement of concessionaires with the technical competence, managerial capacity, and financial resources to expand, re-align, rehabilitate, operate, and maintain the road infrastructure for defined concession tenor for the optimal benefit of the country. The FMW invites interested firms/consortia to participate in a value-added concession initiative. The initiative entails expansion (including interchanges where necessary) and rehabilitation of the entire right of way whilst maximizing its economic viability to ensure the long-term sustainability of the initiative.

3.0 Project Scope

The main scope of the HDMI projects for the 2nd Phase of the PPP scheme includes the expansion, realignment, rehabilitation, and maintenance of the existing road pavements and bridges; construction of interchanges and pedestrian crossings; construction and operations of tolling facilities; installation of weighbridges and operations; installation and operation of intelligent traffic systems for highway remote monitoring; physical patrol of the highway, provision of towing services, ambulance service, Trailer Parks and refuse management. Work must be done in accordance with the Nigerian and globally accepted standards & and specifications. Others include the provision of directional signages, rest areas, highway illumination, etc.

4.0 2nd Phase Corridors

The 2nd Phase scheme covers 30 strategic road corridors packaged into the under-listed lots with an Unbundled Transit Park:


VALUE ADDED CONCESSION
LOT ROUTE DESCRIPTION ROUTE ZONES KM
1 Kano – Katsina A9 NW 90
2 Kano – Kungolani A2 NW 130
3 Zaria – Funtua A126 NW 47
4 Funtua – Sokoto A126 NW 310
5 Sokoto – Ilella A1 NW 87
6 Biu – Gombe Road F129 NE 83
7 Biu – Numan Road A4 NE 153
8 Numan – Jalingo A4 NE 50
9 Yola – Gombe Road A345 NE 266
10 Potiskum – Bauchi A1 NE 305
11 Shuari – Azare A237 NW/NE 162
12 Suleja – Minna Road A124/F126 NC 118
13 Lokoja – Benin A2 NC/SS 291
14 (Oyo S/B) Ilorin– Jebba (Niger State Border) A1 NC 154
15 Minna – Zungeru F126 NC 143
16 Ibadan – Oyo – Ogbomoso - Ilorin A1 SW 173.1
17 Ibadan – Ife-Ilesha Road A122 SW 104
18 Ilesha – Akure – Owo (Dualization) A122 SW 81
19 Ibadan – Abeokuta (Dualization) E1 SW 114
20 Akure– Ado Ekiti F209 SW 68.1
21 Enugu – Abakaliki – Ogoja Highway A343/A4 SE/SS 196
22 Afikpo – Okigwe road F112 SE 66
23 Oba –Nnewi – Okigwe F112 SE 75
24 Benin –Warri A2 SS 95.7
25 Warri –Eleme Junction A231 SS 219
26 Eleme Junction – Eket – Oron F103 SS 84
27 Aba – Ikot Ekpene Road A342 SE/SS 96
28 Odukpani – Itu – Ikot Ekpene A4-1 SS 93.8
29 Akwanga – Jos –Bauchi A3 NC 283
Operation & Maintenance
30 Enugu-Onitsha A232 SE 98
Unbundled Asset Approval
31 Trailer Park in Abia State (Aro-Ngwa, Osisioma Ngwa LGA) SE

5. Central Clearing House (CCH) Toll Operating System

Concessionaires under the HDMI programme would be required to integrate their Toll Systems with that of the Ministry’s Central Clearing House (CCH). The CCH is required to provide efficient toll collection, accountability, and visibility to the FMW of the toll operations as well as ensure uniformity and interoperability. The rationale is to implement a standardized Tolling System that allows for the free flow of traffic across multiple toll roads and seamless processing of the toll transaction, thereby ensuring the continuous operation and maintenance of the roads.

6. PROJECT GOVERNANCE STRUCTURE


S/N PROJECT STEERING COMMITTEE (PSC) MEMBERS PROJECT DELIVERY TEAM (PDT) MEMBERS
I Hon. Minister, FMW/Chairman Perm Sec, FMW/Chairman
II Permanent Secretary, FMW Head PPP Unit/Delegated Chairman
III Honourable Minister of Finance Rep. Director Technical Services, FMF
IV Attorney General of the Federation/Honourable Minister of Justice Rep. Fed. Min of Justice
V Honourable Minister of Environment Rep Fed Min. of Environment
VI Director-General, Infrastructure Concession Regulatory Commission (ICRC) Rep. ICRC
VII Director-General, BPE Rep. BPE
VIII Director-General DG, DMO Rep. DMO
IX Managing-Director, FERMA Rep. FERMA
X Director Highway P&D Rep. Director Highway P&D
XI Director Highway C&R Rep. Director Highway C&R
XII Director Highway B&D Rep. Director Highway B&D
XIII Director Public Procurement Rep. Director Public Procurement
XIV Director Legal Services Rep. Director Legal Services
XV Director ICT Rep. Director ICT
XVI Head PPP Unit – Member/Secretary Secretariat

Federal Ministries, Agencies and Parastatals

INVOLVED IN THE HDMI PHASE II PROJECT;